solarpanelsforlogistics

How much do solar panels for logistics cost?

Indicative UK costs by system size, sub-vertical, and financing route. Updated for 2026.

Warehouse solar is priced per kilowatt of installed capacity, and the figure falls as the system gets bigger. For a UK logistics building in 2026, expect roughly £700 to £900 per kW. Large distribution centres and port warehouses buying at scale often land near £600 per kW, and the smallest last-mile depots sit toward the top of the range because the fixed costs of scaffolding, design, and grid connection are spread over fewer panels. In plain numbers, a 500 kW distribution centre array runs about £350,000 to £450,000, a 1 MW big-box system around £700,000 to £900,000, and a last-mile depot of 100 to 400 kW between £90,000 and £340,000.

The thing that makes logistics solar different from most commercial sectors is that roof area is rarely what limits the system. A modern 100,000 to 500,000 square foot shed can physically hold 1 to 5 MW of panels. What actually sets the size is your daytime electricity baseload and the capacity your DNO will let you connect. Start by pulling half-hourly meter data, because plenty of warehouses turn out to have a surprisingly low daytime baseload between order peaks, and there is no point installing capacity you cannot use on site. Self-consumed solar is worth far more than exported solar, so size to your load, not to your roof.

What changes the price

Three things move the number most. First, roof condition. If your roof is profiled steel in good order, panels go straight on. If it is an older asbestos cement roof, which is common on pre-2000 industrial stock, it needs an asbestos survey and a specialist decision before any PV goes on it: fragile roofs are a serious fall risk (see the HSE guidance), and the usual answer is to replace or over-clad the roof first. The good news is that a combined re-roof and solar project can help the re-roof pay for itself through the energy savings. Second, electrical infrastructure. Many warehouses retain generous supply capacity from their industrial past, which keeps connection costs low, but a constrained site may need switchgear upgrades or a contestable connection. Third, the grid. Systems above the G98 limit of 16 A per phase (3.68 kW single-phase, about 11 kW across three phases) need a G99 application to the DNO, and large installs over 1 MW sometimes need a bespoke network study and reinforcement works.

The hidden costs worth knowing about

A fair quote should include the items that catch people out. DNO connection fees, the structural survey to confirm the roof can carry the array under BS EN 1991-1-4 wind loading, access equipment, and any sprinkler clearance design to the sprinkler designer's and insurer's requirements. On a logistics building, the sprinkler and insurer requirements are not optional extras, they are part of doing the job properly, and an insurer pre-design review belongs in every project so there are no surprises before fabrication. Where a re-roof is needed, it should be a clearly stated line item rather than buried.

How to fund it

There are three routes, and the right one usually depends on whether you own or lease the building. Buying outright, with cash or asset finance, means you own the asset, claim the full capital allowances, and keep every kilowatt-hour of saving. Solar PV qualifies as plant and machinery, so most installs are fully expensed in year one under the 100 percent Annual Investment Allowance up to the £1m threshold, with 50 percent First Year Allowance above. For a limited company that is a tax saving of up to about a quarter of the capex for a company paying the 25% main rate of corporation tax (less at the 19% small-profits rate), taken in year one. Asset finance spreads the cost over five to ten years and can be cash-flow positive from month one for a daytime-occupied warehouse, where the monthly energy saving exceeds the finance payment.

A power purchase agreement, or PPA, is the third route and it suits tenants on shorter leases. A third party owns and operates the system, you pay per kilowatt-hour consumed at a rate below grid retail, and there is no capex; how it appears in your accounts depends on the contract, so ask your accountant. The lease risk sits with the system owner rather than you. The route works for both owner-occupiers and tenants, and where you lease, the BBP Green Lease Toolkit provides a green-lease addendum template to take to your landlord. Full detail on funding routes and the tax reliefs is on our grants and funding page.

How payback is measured, and against what

You will see several numbers quoted. Simple payback is the capex divided by the annual saving, the figure most people lead with. For UK warehouse solar that is indicatively five to six years, and shorter for cold chain, where 24/7 refrigeration pushes self-consumption above 90 percent and payback can come inside four to five years. It is also worth modelling the internal rate of return and net present value over the 25-year asset life, because a five-year payback on an asset that runs for 25 years is a strong long-run return. The benchmark that matters is your grid retail tariff. Every kilowatt-hour you generate and use yourself is a kilowatt-hour you do not buy, which is where the saving comes from.

Timeline and cash flow

Installs like these often run six to nine months from first enquiry to commissioning, and the G99 grid connection is almost always the longest single item, which is why it should be submitted as soon as the structural survey is back. Usually the roof installation happens above the operation, so material handling, picking and despatch can continue. The only outage is typically the final grid synchronisation, a short window usually scheduled for a weekend or planned shutdown.

Cost ranges by sub-vertical

Distribution Centres

Typical system
500-3,000 kW
Project value
£350,000-£2.4m
Indicative payback
5.5 years
Annual generation
460,000-2.75m kWh

Fulfilment Centres (3PL)

Typical system
300-1,500 kW
Project value
£210,000-£1.2m
Indicative payback
5 years
Annual generation
275,000-1.38m kWh

Cold Chain / Refrigerated Warehouses

Typical system
400-1,800 kW
Project value
£280,000-£1.45m
Indicative payback
4.5 years
Annual generation
370,000-1.65m kWh

Last-Mile Depots

Typical system
100-400 kW
Project value
£90,000-£340,000
Indicative payback
5.5 years
Annual generation
92,000-370,000 kWh

Strategic Logistics / Port Warehouses

Typical system
1,000-5,000 kW
Project value
£700,000-£4m
Indicative payback
5 years
Annual generation
920,000-4.6m kWh

Local context: the guides to logistics solar in Leicestershire and logistics solar in Nottinghamshire cover grid connection, planning bodies and logistics roofs for the East Midlands.

Sources and assumptions

The ranges on this page are indicative planning figures, not quotes. They assume a rooftop system on a logistics building from about 100 kW to several MW, a UK-average yield of about 950 kWh per kWp a year and an installed cost of about £600 to £900 per kWp before tax relief, falling with scale. Real prices depend on the roof type and structure, the grid connection and the market on the day. Payback combines avoided electricity purchases at your own contract rates, export income at the rate your supplier sets, and the tax relief you can claim. The rules, rates and dates quoted on this page come from the official pages below. Reliefs, tariffs and deadlines change, so check them before you rely on a figure.

Last checked 31 October 2026.

Send your site details

We reply by email

Tell us about your site and what you need. There is no obligation.

By submitting you agree to our privacy policy. It sets out who can see your enquiry.

Cost questions

How much do solar panels for a warehouse cost in the UK?

A typical warehouse install is £350,000-£2.4m (500 kW-3 MW), at £700-£900/kW depending on system size. Last-mile depots (100-400 kW) range £90k-£340k. Cold-chain and large distribution centres often achieve £600/kW or below at scale. Capital is usually relieved in year one under the Annual Investment Allowance (up to the limit).

What's the payback for cold storage warehouses specifically?

Indicatively 4-5 years, usually the shortest in logistics. 24/7 refrigeration provides ~90%+ self-consumption, and grid electricity is the largest cold-chain operating cost. Round-the-clock refrigeration usually gives cold stores the highest self-consumption of any logistics building type.

Send an enquiry
Send an enquiry